Overview 249 Finchville Turnpike - PV Systems Finchville

The facility monthly summary plot page shows electric generation from all DER projects in the facility, and utility import data if available. The sum of the DER generation and utility import data represents the total facility electric load.

To view data for different dates, select your desired date range and press “Go”.

To download data used to create the monthly summary plot in CSV format, press the download button to the top right of the chart.

Automated data filtering can be enabled or disabled via the control. Filtered data automatically checks to determine if the energy streams measured are consistent with each other (e.g. fuel consumption or heat recovery are reported only when a DER is reporting generated power). Disabling this control shows all data available.

Production data is not in real time and may be delayed as data is periodically reported and uploaded to this website.

The facility monthly summary table shows electric generation from all DER projects in the facility, and utility import and facility electric load data if available.

To view data for different dates, select your desired date range and press “Go”.

To download data from the monthly summary table in CSV format, press the download button to the top right of the table.

Automated data filtering can be enabled or disabled via the control. Filtered data automatically checks to determine if the energy streams measured are consistent with each other (e.g. fuel consumption or heat recovery are reported only when a DER is reporting generated power). Disabling this control shows all data available.

Summary Table

Jul 2021 to Nov 2024
Electric Generation (MWh) Electric Utility Import (MWh) Facility Electric Load (MWh)
Total 21,197 21,197
Jul 2021
305 305
Aug 2021
695 695
Sep 2021
680 680
Oct 2021
308 308
Nov 2021
455 455
Dec 2021
311 311
Jan 2022
443 443
Feb 2022
532 532
Mar 2022
625 625
Apr 2022
502 502
May 2022
600 600
Jun 2022
703 703
Jul 2022
638 638
Aug 2022
764 764
Sep 2022
699 699
Oct 2022
548 548
Nov 2022
462 462
Dec 2022
307 307
Jan 2023
271 271
Feb 2023
495 495
Mar 2023
637 637
Apr 2023
714 714
May 2023
1,078 1,078
Jun 2023
768 768
Jul 2023
769 769
Aug 2023
721 721
Sep 2023
382 382
Oct 2023
11 11
Nov 2023
533 533
Dec 2023
215 215
Jan 2024
174 174
Feb 2024
389 389
Mar 2024
0 0
Apr 2024
527 527
May 2024
532 532
Jun 2024
639 639
Jul 2024
531 531
Aug 2024
708 708
Sep 2024
663 663
Oct 2024
548 548
Nov 2024
314 314

Production data is not in real time and may be delayed as data is periodically reported and uploaded to this website.

The facility time series page shows electric generation from all DER projects in the facility. If available, utility import data is stacked on top to show total facility use. The sum of the DER generation and utility import data represents the total facility electric load.

To view data for another date range or time step, select your desired months and time step and press “Go”. Due to performance constraints, hourly data may only be displayed within a date range of up to one month in length.

To download data used to create the time series plot in CSV format, press the download button to the top right of the chart.

Automated data filtering can be enabled or disabled via the control. Filtered data automatically checks to determine if the energy streams measured are consistent with each other (e.g. fuel consumption or heat recovery are reported only when a DER is reporting generated power). Disabling this control shows all data available.

Times are shown in Eastern Time (ET) and are adjusted to reflect Daylight Saving Time (DST).

Production data is not in real time and may be delayed as data is periodically reported and uploaded to this website.