Skip to Main Content
Search distributed energy resources in New York

Macy's McKinley

Overview Macy's McKinley

The facility monthly summary plot page shows electric generation from all DER projects in the facility, and utility import data if available. The sum of the DER generation and utility import data represents the total facility electric load.

To view data for different dates, select your desired date range and press “Go”.

To download data used to create the monthly summary plot in CSV format, press the download button to the top right of the chart.

Automated data filtering can be enabled or disabled via the control. Filtered data automatically checks to determine if the energy streams measured are consistent with each other (e.g. fuel consumption or heat recovery are reported only when a DER is reporting generated power). Disabling this control shows all data available.

Production data is not in real time and may be delayed as data is periodically reported and uploaded to this website.

NYSERDA requires projects to submit performance data for up to three years. This project has exceeded its required monitoring period, and NYSERDA is no longer gathering project performance data. Solar projects have an expected lifespan of at least 25 years, and energy storage projects have an expected lifespan of at least 10 to 15 years. For more information about the current status of this project, please contact the project owner.

The facility monthly summary table shows electric generation from all DER projects in the facility, and utility import and facility electric load data if available.

To view data for different dates, select your desired date range and press “Go”.

To download data from the monthly summary table in CSV format, press the download button to the top right of the table.

Automated data filtering can be enabled or disabled via the control. Filtered data automatically checks to determine if the energy streams measured are consistent with each other (e.g. fuel consumption or heat recovery are reported only when a DER is reporting generated power). Disabling this control shows all data available.

Summary Table

Nov 2014 to May 2025
Electric Generation (kWh) Electric Utility Import (kWh) Facility Electric Load (kWh)
Total 5,933,252 — 5,933,252
Nov 2014
1,915 — 1,915
Dec 2014
13,885 — 13,885
Jan 2015
10,827 — 10,827
Feb 2015
229 — 229
Mar 2015
32,874 — 32,874
Apr 2015
70,620 — 70,620
May 2015
82,285 — 82,285
Jun 2015
72,187 — 72,187
Jul 2015
89,260 — 89,260
Aug 2015
77,432 — 77,432
Sep 2015
63,352 — 63,352
Oct 2015
41,447 — 41,447
Nov 2015
29,470 — 29,470
Dec 2015
12,478 — 12,478
Jan 2016
11,095 — 11,095
Feb 2016
23,100 — 23,100
Mar 2016
50,336 — 50,336
Apr 2016
62,523 — 62,523
May 2016
85,517 — 85,517
Jun 2016
79,594 — 79,594
Jul 2016
89,578 — 89,578
Aug 2016
82,527 — 82,527
Sep 2016
65,267 — 65,267
Oct 2016
37,551 — 37,551
Nov 2016
27,860 — 27,860
Dec 2016
8,445 — 8,445
Jan 2017
11,032 — 11,032
Feb 2017
31,160 — 31,160
Mar 2017
45,828 — 45,828
Apr 2017
58,722 — 58,722
May 2017
71,559 — 71,559
Jun 2017
85,955 — 85,955
Jul 2017
81,477 — 81,477
Aug 2017
78,357 — 78,357
Sep 2017
63,483 — 63,483
Oct 2017
40,866 — 40,866
Nov 2017
22,522 — 22,522
Dec 2017
5,346 — 5,346
Jan 2018
11,756 — 11,756
Feb 2018
18,450 — 18,450
Mar 2018
26,515 — 26,515
Apr 2018
56,752 — 56,752
May 2018
84,799 — 84,799
Jun 2018
81,166 — 81,166
Jul 2018
92,609 — 92,609
Aug 2018
69,600 — 69,600
Sep 2018
52,525 — 52,525
Oct 2018
28,235 — 28,235
Nov 2018
11,358 — 11,358
Dec 2018
7,007 — 7,007
Jan 2019
11,852 — 11,852
Feb 2019
20,810 — 20,810
Mar 2019
42,131 — 42,131
Apr 2019
54,149 — 54,149
May 2019
67,065 — 67,065
Jun 2019
83,585 — 83,585
Jul 2019
85,522 — 85,522
Aug 2019
81,384 — 81,384
Sep 2019
58,411 — 58,411
Oct 2019
37,831 — 37,831
Nov 2019
13,953 — 13,953
Dec 2019
12,536 — 12,536
Jan 2020
13,739 — 13,739
Feb 2020
19,589 — 19,589
Mar 2020
46,035 — 46,035
Apr 2020
58,661 — 58,661
May 2020
71,626 — 71,626
Jun 2020
97,711 — 97,711
Jul 2020
87,684 — 87,684
Aug 2020
78,571 — 78,571
Sep 2020
57,353 — 57,353
Oct 2020
31,931 — 31,931
Nov 2020
22,540 — 22,540
Dec 2020
11,194 — 11,194
Jan 2021
9,026 — 9,026
Feb 2021
7,871 — 7,871
Mar 2021
61,966 — 61,966
Apr 2021
57,199 — 57,199
May 2021
78,841 — 78,841
Jun 2021
79,045 — 79,045
Jul 2021
73,487 — 73,487
Aug 2021
76,382 — 76,382
Sep 2021
40,146 — 40,146
Oct 2021
33,927 — 33,927
Nov 2021
23,716 — 23,716
Dec 2021
14,070 — 14,070
Jan 2022
5,738 — 5,738
Feb 2022
18,088 — 18,088
Mar 2022
45,841 — 45,841
Apr 2022
60,292 — 60,292
May 2022
76,910 — 76,910
Jun 2022
91,317 — 91,317
Jul 2022
86,357 — 86,357
Aug 2022
72,359 — 72,359
Sep 2022
48,660 — 48,660
Oct 2022
42,329 — 42,329
Nov 2022
18,123 — 18,123
Dec 2022
7,122 — 7,122
Jan 2023
6,267 — 6,267
Feb 2023
26,771 — 26,771
Mar 2023
37,516 — 37,516
Apr 2023
70,217 — 70,217
May 2023
89,063 — 89,063
Jun 2023
73,723 — 73,723
Jul 2023
82,506 — 82,506
Aug 2023
65,932 — 65,932
Sep 2023
62,191 — 62,191
Oct 2023
33,361 — 33,361
Nov 2023
21,048 — 21,048
Dec 2023
12,476 — 12,476
Jan 2024
2,482 — 2,482
Feb 2024
29,439 — 29,439
Mar 2024
42,914 — 42,914
Apr 2024
54,019 — 54,019
May 2024
79,213 — 79,213
Jun 2024
75,893 — 75,893
Jul 2024
33,751 — 33,751
Aug 2024
67,686 — 67,686
Sep 2024
59,299 — 59,299
Oct 2024
46,835 — 46,835
Nov 2024
21,496 — 21,496
Dec 2024
3,771 — 3,771
Jan 2025
7,349 — 7,349
Feb 2025
11,514 — 11,514
Mar 2025
49,548 — 49,548
Apr 2025
58,221 — 58,221
May 2025
55,342 — 55,342

Production data is not in real time and may be delayed as data is periodically reported and uploaded to this website.

NYSERDA requires projects to submit performance data for up to three years. This project has exceeded its required monitoring period, and NYSERDA is no longer gathering project performance data. Solar projects have an expected lifespan of at least 25 years, and energy storage projects have an expected lifespan of at least 10 to 15 years. For more information about the current status of this project, please contact the project owner.

The facility time series page shows electric generation from all DER projects in the facility. If available, utility import data is stacked on top to show total facility use. The sum of the DER generation and utility import data represents the total facility electric load.

To view data for another date range or time step, select your desired months and time step and press “Go”. Due to performance constraints, hourly data may only be displayed within a date range of up to one month in length.

To download data used to create the time series plot in CSV format, press the download button to the top right of the chart.

Automated data filtering can be enabled or disabled via the control. Filtered data automatically checks to determine if the energy streams measured are consistent with each other (e.g. fuel consumption or heat recovery are reported only when a DER is reporting generated power). Disabling this control shows all data available.

Times are shown in Eastern Time (ET) and are adjusted to reflect Daylight Saving Time (DST).

Production data is not in real time and may be delayed as data is periodically reported and uploaded to this website.

NYSERDA requires projects to submit performance data for up to three years. This project has exceeded its required monitoring period, and NYSERDA is no longer gathering project performance data. Solar projects have an expected lifespan of at least 25 years, and energy storage projects have an expected lifespan of at least 10 to 15 years. For more information about the current status of this project, please contact the project owner.