Skip to Main Content
Search distributed energy resources in New York

Delaware River Solar - Cafferty Hill

Overview Delaware River Solar, LLC - 267 Cafferty Hill Rd - PV Systems

The facility monthly summary plot page shows electric generation from all DER projects in the facility, and utility import data if available. The sum of the DER generation and utility import data represents the total facility electric load.

To view data for different dates, select your desired date range and press “Go”.

To download data used to create the monthly summary plot in CSV format, press the download button to the top right of the chart.

Automated data filtering can be enabled or disabled via the control. Filtered data automatically checks to determine if the energy streams measured are consistent with each other (e.g. fuel consumption or heat recovery are reported only when a DER is reporting generated power). Disabling this control shows all data available.

Production data is not in real time and may be delayed as data is periodically reported and uploaded to this website.

The facility monthly summary table shows electric generation from all DER projects in the facility, and utility import and facility electric load data if available.

To view data for different dates, select your desired date range and press “Go”.

To download data from the monthly summary table in CSV format, press the download button to the top right of the table.

Automated data filtering can be enabled or disabled via the control. Filtered data automatically checks to determine if the energy streams measured are consistent with each other (e.g. fuel consumption or heat recovery are reported only when a DER is reporting generated power). Disabling this control shows all data available.

Summary Table

Apr 2022 to Nov 2024
Electric Generation (MWh) Electric Utility Import (MWh) Facility Electric Load (MWh)
Total 19,743 19,743
Apr 2022
134 134
May 2022
455 455
Jun 2022
1,005 1,005
Jul 2022
1,112 1,112
Aug 2022
971 971
Sep 2022
686 686
Oct 2022
672 672
Nov 2022
540 540
Dec 2022
324 324
Jan 2023
203 203
Feb 2023
462 462
Mar 2023
618 618
Apr 2023
745 745
May 2023
1,182 1,182
Jun 2023
894 894
Jul 2023
1,002 1,002
Aug 2023
866 866
Sep 2023
780 780
Oct 2023
580 580
Nov 2023
487 487
Dec 2023
296 296
Jan 2024
206 206
Feb 2024
606 606
Mar 2024
666 666
Apr 2024
700 700
May 2024
789 789
Jun 2024
920 920
Jul 2024
122 122
Aug 2024
0 0
Sep 2024
652 652
Oct 2024
787 787
Nov 2024
283 283

Production data is not in real time and may be delayed as data is periodically reported and uploaded to this website.

The facility time series page shows electric generation from all DER projects in the facility. If available, utility import data is stacked on top to show total facility use. The sum of the DER generation and utility import data represents the total facility electric load.

To view data for another date range or time step, select your desired months and time step and press “Go”. Due to performance constraints, hourly data may only be displayed within a date range of up to one month in length.

To download data used to create the time series plot in CSV format, press the download button to the top right of the chart.

Automated data filtering can be enabled or disabled via the control. Filtered data automatically checks to determine if the energy streams measured are consistent with each other (e.g. fuel consumption or heat recovery are reported only when a DER is reporting generated power). Disabling this control shows all data available.

Times are shown in Eastern Time (ET) and are adjusted to reflect Daylight Saving Time (DST).

Production data is not in real time and may be delayed as data is periodically reported and uploaded to this website.